Church Building Expansion - The Plan

Phases

Phase one: 
1. Multipurpose Activity Center:  Indoor Gym   
2. Bathrooms for multipurpose activity center
3. Bathroom fittings for the new chapel
4. Foundation for classrooms/office/new chapel
5. Circular driveway (paved, one direction)

Phase two A: 
Built Entire shell.

Phase two B: 
Complete 14 new classrooms, 4 new offices.

 Phase Three: 
1. Complete the New Chapel with 355 seats.
2. Improve gravel parking lot.

Timeline for Phase One and Phase Two A

  • Project promotion & fundraising,
    Dec 2021

  • Design and Build Contractor searching, Apr 2022

  • Detail design for building permit,
    Sept 2022

  • Apply for building permit,
    Jun 2023

  • Building permit Approval,
    Apr 2024

  • Construction begins,
    May 2024

  • Construction complete,
    Dec 2024

  • Building occupancy approval,
    Jan 2025